1.0.1 This code is formulated with a view to strengthen the installation quality management of coking and chemical mechanical equipment engineering, and to unify the acceptance of installation of mechanical equipment engineering as well as to guarantee the engineering quality.
1.0.2 This code is applicable to the installation quality acceptance of mechanical equipment engineering of coal treatment equipment, coking furnace system, dry quenching system and recovery system of gas purification and coking products.
1.0.3 Requirements for Installation quality stated by technical document and contract agreement document adopted in the installation of coking and chemical mechanical equipment engineering shall not be inferior to those specified in this code.
1.0.4 The installation quality acceptance of coking and chemical mechanical equipment engineering shall not only comply with those specified in this code, but also comply with those specified in the current national standards concerned.