1.1.1 Brief overview of profile for plant building
Explain enterprise property, outline construction background, investment limit, progress requirements and development prospects.
1.1.2 Design basis
1 Design assignment of approved construction project (feasibility study report) and official documents.
2 Overall design and official documents (when having overall design), name and contract number of technology acquisition (when having technology acquisition project) contract.
3 Design contract signed with owner (construction organization).
4 Design condition meeting summary with owner (construction organization).
5 Approval documents of government departments for such aspects as fire fighting, environmental protection, labor safety and sanitation.
6 Raw materials, public works supply report and other relevant documents and agreement required by owner (construction organization) providing project implementation.
7 Scientific test report and technical evaluation report of adopted new process, new technology, new facilities and new materials in the design.
1.1.3 Design guidelines
1 Implement national capital construction policy, make design practical with advanced technology, economic and rational, safe and useable.
2 Implement the measure and effect of integration, outdoors, light type, socialization and localization.
3 Scope and reason of introducing technology and equipment.
1.1.4 Design scope and design division
1 List the items included in the design, and explain according to such sequence as production plant, auxiliary device, public works, communication and transportation and communication, work and living and welfare facilities.
2 When two or more design organizations undertake design, the engineering project undertook undertaken by each design organization and mutual link relation shall be definite.
1.1.5 Construction scale and product program
1 Designed productive capacity, production potential and development space of plant or device.
2 Product variety, specification and quantity.
1.1.6 Specification of main raw materials and fuel as well as their consumption and source.
1.1.7 Production method and total process of whole plant
Discuss technological sophistication and economical rationality; emphasize to explain technological feature, safety measures and energy conservation measures.
1.1.8 Plant site profile
1 Geographical position of plant area, current transportation and communication conditions.
2 Floor space and occupied cultivable area of whole plant.
3 Conditions of removing buildings and structures and other special problems.
1.1.9 Public works and ancillary works
1 Consumption of such power as water, electricity, steam and gas of plant and their source.
2 Determination of storage, loading and unloading mode, storage period, warehouse or storage location of raw materials and products in plant.
3 Plant maintenance quantity, composition and scale of plant repair workshops, repair capacity and external cooperation degree.
1.1.10 Environmental protection and comprehensive utilization
1 Environmental condition of plant area, pre-assessment for environmental quality after building plant.
2 Implement the measures of national environment policy act and relevant documents, reliability, viability and benefit after implementation of "three wastes" governing and comprehensive utilization design scheme.
HG/T 20688-2000 The following standards are cited: