1 Scope
This Part specifies the fundamental principles, contents and requirements of the design for dust prevention and control of coal handling system in fossil fuel power plant.
This Part is applicable to dust prevention and control design of new, extended or rebuilt coal-fired power plant equipped with unit of 50MW~600MW unit capacity. It may apply the dust prevention and control design for coal-fired power plant with under 50MW unit capacity, as well as for new or extended coal-fired power plant with a unit capacity of over 600MW by reference.
2 Normative References
The following documents contain provisions which, through reference in this text, constitute provisions of this standard. For dated reference, subsequent amendments to, or revisions of, any of these publications do not apply. Parties to agreements based on this Part are encouraged to investigate the possibility of applying the most recent editions of the standards indicated below. For undated references, the latest edition of the normative document referred to applies.
DL/T 5187.2-2004 The following standards are cited:
DL/T 5187.2-2004 Cited by the following standards: