Article 1.0.1 This is to formulate the Code to ensure the construction quality of the installation engineering and safe operation of the earthed device and improve the technology level of the construction.
Article 1.0.2 The Code is applied to the construction and acceptance of installation engineering of electric equipment’s earthed device.
Article 1.0.3 The installation engineering of the earthed device should be conducted according to the approved design.
Article 1.0.4 The adopted equipment should conform to the national applicable technology standard with qualified certificate.
Article 1.0.5 Safe technology measure of the construction should conform to the Code and applicable regulation on safe technology standard.
Article 1.0.6 The installation of the earthed device should be in conjection with the construction of building engineering. Authority departments should finished medium examination and acceptance record of any and all concealed parts.
Article 1.0.7 The construction and acceptance of the earthed device should conform to the Code and other applicable standards and regulations.