The Code is established with the end of supervising construction and acceptance of machinery fitting engineering, ensuring quality and security, promoting technical advancement and enhancing economic benefits.
Article 1.0.2
This Code is compliable to construction and acceptance of various machinery fitting engineering, from uncasing to the zero-load test run of equipment. For equipment requiring loads for test run, the construction and acceptance will be from uncasing to load test run.
Article 1.0.3
Equipment installation projects ought to be constructed according to designs. During construction, if irrationalities are discovered in designs, amending suggestions ought to be put forward in time and the construction can only be recovered according to the altered design after the alternation design is approved.
Article 1.0.4
Materials mainly used for the installed mechanical equipment or for important places of the equipment ought to be in compliance with provisions of the design and product standards and acquired qualified certification.
Article 1.0.5
Different kinds of measurement apparatuses, detection apparatuses, devices, instruments and equipment applied in installation ought to be in compliance with current state weights and measures laws and regulations and their accuracy classes ought to be no lower than those of examined targets.
Article 1.0.6
For concealed works in the installation process, inspections ought to be carried ought before the concealed works are performed and records ought to be made. Continuous installation can only be carried out after it is tested qualified.
Article 1.0.7
During installation process, self-check, cross-check and professional checks ought to be carried out. Inspections ought to be taken in each process and records ought to be made. In the acceptance of works, records ought to be taken as evidences.
Article 1.0.8
Construction of equipment installation projects ought to in compliance with this Code as well as with regulations of national current standards and codes.